Report Finds Anthropic's 2028 Power Mostly Gas and Coal

A nonprofit estimates Anthropic's 2028 data centers will draw 87 percent of their power from gas, with coal supplying most of the rest.

Edited by Ryan Elliott Dennis5 min read · 1,047 words · 6 sources
The gas-fired Ocotillo Power Plant lit up at night in Tempe, Arizona
“By 2028, keeping Claude running could pump out as much carbon dioxide as every power plant in California burned in a single year. Does one nonprofit's math on Anthropic's own numbers hold up?”

A nonprofit says Anthropic's data centers will run mostly on gas and coal by 2028. The Better Data Center Project published the estimate on Nov. 16, 20261. It modeled, site by site, which power plants will likely ramp up to feed Anthropic's new electricity demand.

The group's mid case: 87 percent gas, 11 percent coal, and zero percent new U.S. renewables1. Anthropic has signed zero U.S. clean-power deals for the group to count instead.

Word of the finding spread fast. A Hacker News post carrying the Better Data Center Project's number climbed to the site's front page by Saturday afternoon5. One of the comments pushed back hard enough that it reached X.

Hero.S@aka_ssy

Anthropic’s 2028 AI buildout is being modeled as 87% gas-powered and 11% coal-powered. That is not a claim that every Claude query burns coal; it’s an estimate of the marginal power likely to meet contracted U.S. data-center load, including on-site generators and grid plants.… pic.twitter.com/PJ5PP3NtR6

A chart from the Better Data Center Project showing Anthropic's modeled 2028 power sources
Open on X (opens a new tab)

Hero.S, whose post carried the 87 percent figure onto X, called it a model of marginal power for new demand alone, apart from any single query Claude answers.Post by Hero.S (@aka_ssy) on X, Nov. 22, 2026

Hero.S, the X user who wrote that post, made a careful point. The 87 percent figure describes marginal power, the extra electricity a grid or a generator supplies when demand rises. Every single Claude answer burning coal would be a much bigger claim, and a different one.

What the model counts

BYOP means "bring your own power." A utility hookup can take years. So an AI company pays a developer to build a private plant right next to its data center instead. Anthropic uses this model for part of its buildout.

About 2.5 of Anthropic's 9.6 contracted U.S. gigawatts comes from this on-site, behind-the-meter gas1. That is roughly a quarter. The rest draws from the regular grid. There, the Better Data Center Project still counts gas and coal plants as the ones most likely to answer new demand.

The Bastrop Energy Center, a gas-fired power plant in Bastrop County, Texas
The Bastrop Energy Center in Bastrop County, Texas, burns natural gas in two combustion turbines. Anthropic's own gas supplier, OnePWR Solutions, is based in the same state.Larry D. Moore / Wikimedia Commons, CC BY 4.0

Coal enters the count a different way. The model assigns 11 percent of Anthropic's 2028 power to coal plants on the margin of regional grids. Those plants ramp up when demand climbs past what cleaner plants can cover1.

Run the mid case forward and Anthropic's power use could emit 32 million metric tons of carbon dioxide equivalent in 20281. The full range runs from 17 to 38 million tons. That mid case alone could top the 31.1 million tons California's entire power sector emitted in 2024.

It could also exceed Meta, Microsoft and Google's combined 2025 emissions of 32.9 million tons, measured the same way. That measure is called Scope 2: the carbon tied to electricity a company buys, apart from the carbon it burns on-site.

Anthropic's modeled 2028 power runs 87 percent on gas, 11 on coal

Modeled share of power for Anthropic's contracted U.S. data centers in 2028, Better Data Center Project

Each slice is a modeled share of Anthropic's 2028 power. The magenta slice is gas, the blue slice is coal, and the gray slice is every other source, including renewables, left out of this model entirely.

Anthropic's only clean-power commitments run through Norway and Canada, so the model's U.S. count skips renewables entirely.

Data through Nov. 16, 2026.

Source: Better Data Center Project [1]. Chart by Kelly Dennis.

The numbers behind this chart
ItemValue
Gas87%
Coal11%
Other sources2%
Whole100%
The cooling tower at the Michigan City Generating Station, a coal and natural gas power plant in Indiana
The Michigan City Generating Station in Indiana burns both coal and natural gas, the two fuels the Better Data Center Project models as Anthropic's main 2028 power source.Tony Webster / Wikimedia Commons, CC BY 2.0

The group adds one more figure. Gas and coal plants release fine particles and nitrogen oxide near the communities around them. That pollution could cause $2 billion to $3 billion a year in health damage1.

Anthropic's 2028 emissions could top all of California's power plants

Carbon dioxide equivalent, million metric tons a year, Better Data Center Project's mid case against 2024 and 2025 totals

Each bar is one year's carbon dioxide total. The magenta bar is Anthropic's modeled 2028 mid case, and the gray bars are the real totals the group measured it against.

Anthropic's figure is a 2028 estimate inside a 17 to 38 million ton range; the other two bars are measured totals from different years.

Data through Nov. 16, 2026.

Source: Better Data Center Project [1]. Chart by Kelly Dennis.

The numbers behind this chart
ItemValue
Anthropic, 2028 mid case (estimate)32 Mt
California power plants, 202431.1 Mt
Meta, Microsoft, Google, 202532.9 Mt

Anthropic's own words

The company's IPO filing skips a fuel-mix percentage. Runtime Wire checked the prospectus directly. It found gas-fired sites, uncapped fuel costs and a $500 million power-contract guarantee3. Every fuel sits folded into one combined figure.

Here is why Anthropic reaches for gas at all. "Electric grid infrastructure in the United States and other countries was not designed to accommodate the rapid increase in demand associated with AI development," the company told investors in its S-14. That line is Anthropic's own case for building private power.

Anthropic signed a $3.4 billion deal in September. The buyer was Texas-based OnePWR Solutions, for 1.7 gigawatts of gas turbines14. Dario Amodei, Anthropic's chief executive, built the company on a promise of safer AI. Its prospectus names zero renewable-power deals in the United States to set against that bet on gas.

The case against the number

Charlie Cray, senior strategist at Greenpeace USA, read the report as confirmation of something he already suspected. "At least they admit that climate change is a threat when they say it's a risk to their own operations, but they're not taking responsibility for their own contribution," Cray said2.

Cray's complaint reaches beyond gas alone. It covers what Anthropic has kept off the page. "The entire sector needs to be scrutinized closely as to what choices they make and how much transparency is in their reporting — which in this case, is not a lot," he said2.

He wants a deadline attached to that disclosure. "They shouldn't be building data centers that are powered by natural gas without a timeline for phasing that out and replacing it," Cray said2.

Travis Miller, a senior equity analyst at Morningstar, reads the same buildout from the money side. "Utilities and investors are watching the landscape very closely because data center growth is a key part of the investment story for utilities in the coming years," Miller said4. A utility's shareholder counts Anthropic's gas contracts as growth. Cray counts the same contracts as a company locking in the fuel it says the world should leave behind.

What to do

Ask your AI vendor where its power comes from before you sign a multiyear deal. A supplier's own climate pledges mean less than the generators actually feeding its data centers.

Watch Anthropic's next SEC filing for an actual fuel-mix number. If the company discloses one, compare it against this nonprofit's 87 percent gas estimate and see how close the outside model came.

By the numbers

  • 87 percent: Share of Anthropic's contracted 2028 U.S. data center power the Better Data Center Project models as gas-fired1.
  • 32 million metric tons: Anthropic's 2028 mid-case carbon dioxide estimate, inside a range of 17 to 38 million1.
  • 11 percent: Share of that same power it models as coal-fired, with zero credited to new U.S. renewables1.
  • 31.1 million tons: Carbon dioxide California's entire power sector emitted in 2024, a total the mid case could top1.
  • 2.5 of 9.6 gigawatts: The on-site, behind-the-meter gas share of Anthropic's contracted U.S. capacity1.
  • $3.4 billion: Anthropic's September deal with OnePWR Solutions for 1.7 gigawatts of gas turbines4.
  • $500 million: The power-contract guarantee Anthropic's prospectus discloses, alongside uncapped fuel costs3.
  • $2 billion to $3 billion: Estimated yearly health damage from the fine particles and nitrogen oxide these plants release1.

What to watch

Watch Anthropic's next 10-K or prospectus amendment for an actual fuel-mix number. That single disclosure would settle the gap Runtime Wire found3.

A U.S. renewable power contract matters just as much. The Better Data Center Project's zero-renewables count stands only until Anthropic signs one1. One signed deal would move the model's number more than another round of argument could.

Sources

  1. Better Data Center Project, "How AI Is Powered: A Breakdown of BYOP and Grid Power," Nov. 16, 2026, https://betterdatacenterproject.com/2026/11/16/how-ai-is-powered-a-breakdown-of-byop-and-grid-power/
  2. Kate Yoder, "Even the 'Good Guys' of AI Are Locking in Fossil Fuels," Grist, Nov. 19, 2026, https://grist.org/accountability/anthropic-alignment-ai-fossil-fuels-climate-change/
  3. Morgan Laning, "Anthropic's Prospectus Confirms On-Site Gas Power at Some Planned Data Centers, but Gives No Fuel Mix," Runtime Wire, Nov. 22, 2026, https://runtimewire.com/article/anthropic-s-prospectus-confirms-on-site-gas-power-at-some-planned-data-centers
  4. Jeff Young, "Anthropic Debuts in an Uneasy Energy Week," Latitude Media, Nov. 18, 2026, https://www.latitudemedia.com/news/anthropic-debuts-in-an-uneasy-energy-week/
  5. "87% of the Anthropic power will come from gas and 11% from coal in 2028," Hacker News, Nov. 22, 2026, https://news.ycombinator.com/item?id=50597612
  6. Hero.S (@aka_ssy), post on X, Nov. 22, 2026, https://x.com/aka_ssy/status/2124451368991949239

Header photo: Alan Stark from Goodyear, AZ, United States / Wikimedia Commons, CC BY-SA 2.0

Cite this piece

Kelly Dennis, "Report Finds Anthropic's 2028 Power Mostly Gas and Coal," Ai Lately, Nov 22, 2026, https://ailately.com/articles/anthropic-2028-power-gas-coal

Tags: Anthropic · data centers · gas power · coal power · emissions

Related, lately

More

Keyboard

j k
Move through a list
Enter
Open the selected piece
/
Search, and browse the columns
g then r
Right Now
g then a
Articles
g then s
The Signal
g then o
Opinion
g then b
Analysis
g then p
People
?
This sheet
Esc
Close

AI Right Now is free with an account.The Citation Audit is free with an account.Skills are free with an account.Tutorials are free with an account.You have read your 3 free articles.

Every article and comic, AI Right Now, the Citation Audit, Skills and Tutorials.

Join Ai Lately for free

Join with Google or your email. Already a member? Sign in

Press anywhere else for the home page.