Nebius told investors on Nov. 12 that it will spend $40 billion to $45 billion next year on AI data centers1. Most of that money is supposed to arrive before the computers do, from customers who pay in advance.
One of those customers is Microsoft. Its contract with Nebius runs up to $19.4 billion2. Microsoft's contract already missed its first delivery dates.
Who Pays for the Build
Nebius Group rents out computers built for AI work. The company buys the chips for a customer's workload, builds the site around them, and carries the debt behind both.
Founder and chief executive Arkady Volozh told investors the model is working. "Prepayments on Q3 agreements covered more than 100% of the associated capex," Volozh said in the company's own letter to shareholders1. He added a target for the business as a whole: "We expect to reach pre-tax breakeven by the end of 2027."
That is the pitch. A customer signs a multiyear deal and pays part of it up front. Nebius uses that cash, plus loans backed by the signed contract, to pour concrete and buy chips. The customer's AI workload shows up later, once the building is live.
Nebius's math only holds if the building goes live on time.
The Gap in Nebius's Own Math
Nebius expects prepayments and asset-backed loans to cover 75 to 85 percent of its 2027 spending1. Take the middle of both ranges. That is $34 billion of a $42.5 billion budget.
Nebius raises its 2027 spending plan 57 percent above 2026's $27 billion
Nebius's own capital expenditure guidance, billions of dollars, fiscal years 2026 and 2027
Each column is Nebius's own guidance for the year; the lighter 2027 column is an estimate, the $42.5 billion midpoint of its $40 billion to $45 billion range.
The 2027 figure is an estimate, the midpoint of Nebius's own $40 billion to $45 billion guidance.
Source: U.S. Securities and Exchange Commission [1]. Chart by Ryan Elliott Dennis.
The numbers behind this chart
| Item | Value |
|---|---|
| 2026 | $27B |
| 2027 (estimate) | $42.5B |
Eighty percent still leaves 20 percent open. On a $42.5 billion plan, that gap runs to $8.5 billion1. Nebius kept its plan for closing that gap private.
Nebius's own math still leaves $8.5 billion of 2027 spending uncovered
Where Nebius expects its $42.5 billion in planned 2027 capital spending to come from, at the midpoint of its own guidance
The accent slice is prepayments and asset-backed financing, the share Nebius itself projects; the gray slice is the rest it still has to raise.
Source: U.S. Securities and Exchange Commission [1]. Chart by Ryan Elliott Dennis.
The numbers behind this chart
| Item | Value |
|---|---|
| Prepayments and loans | $34B |
| Still uncovered | $8.5B |
| Whole | $42.5B |
That $8.5 billion sits close to a number an outside critic reached a different way, using Nebius's own disclosures. The two estimates started from different math. They still land in roughly the same place.
A Deadline Microsoft Is Still Waiting On
Nebius's largest named customer contract is with Microsoft. The deal runs up to $19.4 billion if Microsoft takes every option in it2. Most of that capacity sits at a site in Vineland, New Jersey.

Vineland was supposed to deliver its contracted capacity across 2025 and 20262. Instead, slightly more than half will arrive by the end of 2026. The rest slides to the second quarter of 20275.
A power shortage at the site caused the holdup. Nebius's colocation partner there, a firm called DataOne, wound down a temporary generator earlier than Nebius expected1. Permanent fuel cells from Bloom Energy had to ramp up fast to cover the gap5.

Volozh addressed the point directly on the earnings call. "Building at this scale is hard, and delays are part of our industry right now," he said. "We are not immune"2.
Microsoft's contract has teeth for exactly this case. After a grace period, Nebius can lose that part of the deal unless it has a substitute ready. Late penalties apply too5. Both companies have stayed quiet about whether either remedy has fired.
Two Readings of the Same Prepayment
Marc Boroditsky, Nebius's chief revenue officer, argues the financing survives the delay. "Prepayments attached to new contracts signed in the third quarter more than cover the cost of developing the capacity required to fulfil them," Boroditsky said on the earnings call4. By his account, each new deal pays for its own construction before the first bill comes due.
Daniel Romero reads the same numbers and reaches the opposite worry. Romero holds Nebius shares and publishes a research newsletter on the stock. "The most important one is in Vineland, where there's a very significant delay of 1–2 quarters on up to about 150 MW," Romero wrote. "The reason? Incompetence by DataOne, their colocation provider"3.
Wall Street split the difference. Citi's Tyler Radke cut his price target to $215 from $265 on Nov. 13. He kept his Buy rating in place6.
TipRanks@TipRanksNebius $NBIS price target lowered to $215 from $265 at Citi
Citi analyst Tyler Radke lowered the firm's price target on Nebius to $215 from $265 and keeps a Buy rating on the shares.
The company reported "solid" Q3 reuslts but trimmed its near-term revenue guidance on site… pic.twitter.com/X2xxpAtxEX
Microsoft is watching more than Nebius. Bloomberg reported this month that Microsoft tightened its oversight of capacity projects at Nebius and two rival neoclouds4. Microsoft also dropped its option to anchor one rival's planned Texas site after power delays there too.

What to Do
Ask a vendor what share of next year's budget rides on prepayments due, and what share rides on debt. Nebius just gave investors both numbers in public. Most private vendors keep them to themselves until asked.
Read a vendor's contract for its delivery dates first, ahead of its topline value. Microsoft's $19.4 billion figure survived the Vineland delay. The dates attached to it slipped instead. A penalty clause only protects a buyer who tracks the dates it was supposed to trigger on.
By the Numbers
- $40 billion to $45 billion: Nebius's 2027 capital spending guidance, issued Nov. 12, 2026, to add more than 1 gigawatt of capacity1.
- More than 100 percent: Q3 2026 capacity costs that customer prepayments covered, up from 50 to 60 percent a quarter earlier1.
- $27 billion: Nebius's revised 2026 capital spending, up from its earlier $20 billion to $25 billion range1.
- 75 to 85 percent: the share of 2027 capex Nebius expects prepayments and asset-backed financing to cover1.
- $19.4 billion: the ceiling of Nebius's contract with Microsoft, reached only if Microsoft exercises its full option2.
- Q2 2027: the new delivery date for the New Jersey capacity Microsoft originally contracted for 2025 and 202625.
- 150 megawatts: the Vineland capacity Daniel Romero says is running one to two quarters late3.
- $215: Citi's price target on Nebius after the delay, cut from $265 on Nov. 13, 2026, with its Buy rating kept6.
What to Watch
Watch whether Nebius names a specific lender or bond for the $8.5 billion gap in its own math. So far it has given only a percentage range. The second quarter of 2027 is the new date for Microsoft's remaining New Jersey capacity; track whether it ships on time5. A second missed date would test a termination clause both companies have left alone so far.
Sources
- Nebius Group N.V., "Form 6-K, Letter to Shareholders, Third Quarter 2026," U.S. Securities and Exchange Commission, Nov. 12, 2026, https://www.sec.gov/Archives/edgar/data/0001513845/000110465926126008/tm2629571d1_ex99-2.htm
- Rebecca Bellan, "Nebius tests the neocloud playbook with $40 billion in planned spending," TechCrunch, Nov. 12, 2026, https://techcrunch.com/2026/11/12/nebius-tests-the-neocloud-playbook-with-40-billion-in-planned-spending/
- Daniel Romero, "Is Nebius Fucked?," Hypertech Invest (Substack), Nov. 13, 2026, https://hypertechinvest.com/p/is-nebius-fucked
- Samuel Nwite, "Nebius's $40bn AI Infrastructure Spending Plan Faces Delays, Microsoft Contract Risks," Tekedia, Nov. 13, 2026, https://www.tekedia.com/nebius-40bn-ai-infrastructure-spending-plan-faces-delays-microsoft-contract-risks/
- Editorial Staff, "Nebius Stock: Power Bottleneck at Vineland Puts Microsoft's $19.4 Billion Deal to the Test," boerse-global.de, Nov. 14, 2026, https://www.ad-hoc-news.de/boerse/news/unternehmensnachrichten/nebius-stock-power-bottleneck-at-vineland-puts-microsoft-s-19-4-billion-deal-to-the-test/70513608
- TipRanks, "Nebius $NBIS price target lowered to $215 from $265 at Citi," X, Nov. 16, 2026, https://x.com/TipRanks/status/2122303472032764303